Jilai high-speed railway enters the stage of operation test: the design speed is 350 kilometers per hour.

2025-01-15 Update From: SLTechnology News&Howtos shulou NAV: SLTechnology News&Howtos > IT Information >

Share

Shulou(Shulou.com)11/24 Report--

CTOnews.com November 17 news, according to the people's railway, November 17 at 8:20, with the 55301 test train from Jinan East Station, Jinan to Laiwu high-speed railway officially entered the operation test stage, the line opened operation into the countdown.

CTOnews.com learned that Jinan-Laiwu High-speed Railway is located in Jinan City, Shandong Province, with a total length of 117.49 kilometers and a design speed of 350 kilometers per hour. There are 6 stations in Jinan East, Licheng, Zhangqiu South, Xueye, Laiwu North and Gangcheng along the whole line, which are connected with Shiji High-speed Railway and Jiqing High-speed Railway through Jinan East Railway Station and connected to the national high-speed railway network.

Operation test is to complete the test of track, catenary, communication, information, customer service and other equipment by setting typical fault, emergency rescue scenario, EMU tracking interval time, interval operation time and other tests, so as to verify the stability and ability of each system, so that all professionals can receive sufficient practical training to meet the requirements of normal operation.

The operation test of Jinan-Laiwu high-speed railway is divided into four stages. The first is the fault simulation test stage, which mainly sets typical fault scenarios for simulation exercises to verify the fault handling capability of the overall system and improve the rapid response and collaborative processing capability of the system under equipment failure or severe weather conditions. Second, emergency rescue drill stage, mainly through the emergency, personnel evacuation, emergency rescue, emergency maintenance and other aspects of the drill, test each system Incident Response Service and support capabilities. The third is the test stage of operation diagram parameters, mainly including EMU train tracking interval time test, interval operation time test, start-stop additional time test, etc. The fourth is the driving test stage according to the diagram, mainly through the driving test according to the diagram, the equipment operation is tested, the stability of each system is verified, so that the professional operators can receive sufficient practical training, master various rules and regulations, be familiar with the work flow, and meet the requirements of normal operation.

After the completion and opening of Jinan-Laiwu High-speed Railway, it will further improve the structure of Shandong high-speed railway network and facilitate the travel of people along the line. It is of great significance to build Shandong's "provincial capital economic circle on track" and promote coordinated regional development.

Welcome to subscribe "Shulou Technology Information " to get latest news, interesting things and hot topics in the IT industry, and controls the hottest and latest Internet news, technology news and IT industry trends.

Views: 0

*The comments in the above article only represent the author's personal views and do not represent the views and positions of this website. If you have more insights, please feel free to contribute and share.

Share To

IT Information

Wechat

© 2024 shulou.com SLNews company. All rights reserved.

12
Report